Rīga-Bolderāja train line will have to wait for next year

Although the construction of the railway line to Bolderāja has been completed and the new stations in Iļģuciems and Bolderāja could soon be put into service, passenger trains are unlikely to run on this route this year, Latvian Radio reported on November 20.
On a weekday morning, not far from the Central Railway Station, Latvian Radio spotted an electric train standing still, with Bolderāja listed as its final destination. No passenger trains have run there for 67 years.
“This display appeared due to a technical error. We are fully prepared to provide services to Bolderāja. In this instance, our train driver had temporarily selected the incorrect destination, which was, of course, corrected,” explained the company “Vivi”.
They are ready to start services as early as December, but are waiting for “Latvian Railways” to complete the work.
“After that, we are awaiting a decision from the Public Transport Council regarding the scope of the contract for this railway line and, accordingly, the available funding. So at the moment, these matters fall within the remit of the Road Transport Directorate. We are in no position to confirm or comment on the start date,” said the company’s spokesperson, Dace Zaldāte-Rozentāle.
It is not yet possible to launch services between the city centre and Bolderāja – this is the response given to Latvian Radio by the Road Transport Directorate, which has not yet received an opinion from the State Railway Technical Inspectorate. The Directorate does not know when this might be received. Until the opinion is available, they will not refer this matter to the Public Transport Council. However, preparatory work is underway at the Directorate.
“If we consider how long it actually takes to prepare the matter for submission to the Public Transport Council, and how often the Public Transport Council is convened – at least once a month according to the regulations – then, of course, looking at it objectively, it is highly likely that we will not be making such a decision this year,” said Tomass Beikulis, Head of the Public Transport Department at the Authority.
Trains to Bolderāja will not start running immediately following the Public Transport Council’s decision.
“Of course, the service provider also needs time to prepare. In the railway infrastructure, the tracks are interconnected. Consequently, we need to identify the times when the tracks are free and can be used. The speed of movement depends on this. We will be able to prepare a final proposal for the council and then implement it accordingly after a certain period of time. I won’t venture to say how soon [the line might open]. There are still many variables that we cannot accurately predict at present,” explained a spokesperson for the management.
Admittedly, two months ago, Artis Grinbergs, head of “Latvian Railways”, mentioned quite precise dates to Latvian Television for when the line is planned to open – mid-October or early November.
Dagnis Samausks, acting director of project management at “Latvijas dzelzceļš”, explained that all construction work had been completed within the aforementioned timeframe, but this did not mean that trains were already able to run.
There has been a delay in finalising the paperwork for the stations at Iļģuciems and Bolderāja. The two new platforms have cost 1.2 million euros.
“We have discussed with the construction engineer that a certificate of readiness for commissioning could be issued within the next week. This will then be submitted to the State Railway Technical Inspectorate to obtain final approval for commissioning,” explained Samausks.
Meanwhile, the electrification of the line, worth over 14 million euros and fully funded by the European Union, has already been put into operation. Samausks hopes that the Inspectorate will make its final decision in early December. He did, however, reveal that no funds have been allocated this year for the opening of the new route.
Beikulis, a representative of the Road Transport Directorate, subsequently replied in writing that the financial matter falls within the remit of the Public Transport Council:
“Expenditure for this is planned in next year’s budget, but no decision has yet been taken by the Cabinet of Ministers regarding the total funding; however, the Road Transport Directorate has included the necessary funding in this report.”
The Directorate estimates that a journey from the city centre to Bolderāja, stopping at Torņakalns, Zasulauks and Iļģuciems, will take possibly more than 20 minutes, which is about 10 minutes less than by a “Rīgas satiksme” bus. Admittedly, the trains will not run as frequently. It is forecast that there could be seven services a day in each direction, but the final decision will be taken by the Public Transport Council.
Seen a mistake?
Select text and press Ctrl+Enter to send a suggested correction to the editor
Select text and press Report a mistake to send a suggested correction to the editor
Материал изданияLSM English
Читать в оригинале